The Saga Continues: June
First Stage Basement Shotcrete June 4, 2007
Final layer on basement walls June 5, 2007
Smoothing Basement Walls June 6, 2007
Preparations for ceiling/floor June 7, 2007
Preparing for the floor pour June 8, 2007
Preparing for the floor pour June 9, 2007
First floor preparation June 11, 2007
Working on Floor June 12, 2007
Working on Floor June 13, 2007
More on the floor and a whole lot of electrical June 14, 2007
Rebarring the floor June 15, 16, 2007
Spacing the Rebar June 18, 2007
Getting Ready For the Big Pour June 19, 2007
The Big Pour of June 20, 2007 pg 1
The Big Pour of June 20, 2007 pg 2
After the Pour June 20, 2007 pg 3
Outlining the walls June 21, 2007
Removing forms & other clean up June 22, 2007
Removing 2x4 jungle from basement June 28, 2007
Removing wood from basement June 29 & 30, 2007
July 2, 2007and 7/5/07